About "house of all" of small temporary housing maintenance progress (at September 26, 2017)

 Maintenance work progress of "person of of all" which utilizes "Japanese foundation our town foundation" from this January, and stimulates maintenance in small temporary housing,

According to the next table, seven in total are completed as of today.
 "House of all" which we maintained after the Kumamoto earthquake having this ※As for this, 91 maintenance in total becomes completion.

 

※Based on the Disaster Relief Act, maintenance of 84 "houses of all" is completed in temporary housing 62 housing complex of the prefecture until now.
  (about maintenance of "house of all" in temporary housing /https://www.pref.kumamoto.jp/kiji_16340.html)

 

 

(information materials)

PDF Construction of "house of all" starts in 170525_ Misato-machi, small temporary housing complex of Mifune-machi! We open with the other window(PDF: 355.6 kilobytes)

  •  

 

Small scale temporary housing (11 housing complexes in total) which maintains "house of all"

The municipalities name of a village

Housing complex name

Progress

The design situation

Construction start day

Completion day

Kumamoto-shi

Jonanchou 2 chome temporary construction housing complex (16)

Design completion

May 29

July 22

Uto-shi

Border second temporary housing complex (14)

Under design

Undecided

Undecided

 

Border third temporary housing complex (12)

Under design

Undecided

Undecided

 

New Matsubara temporary construction housing complex (18)

Under design

Undecided

Undecided

Uki-shi

Territory temporary construction housing complex (ten)

Design completion

June 20

September 25

 

Magano Hasegawa temporary construction housing complex (13)

Design completion

June 20

September 25

Aso-shi

Uchinomaki temporary construction housing complex (19)

Design completion

June 15

September 22

Misato-machi

kusunoki flat temporary construction housing complex (15)

Design completion

May 29

September 5

Minamiaso-mura

Room second temporary housing complex (13)

Under design

Undecided

Undecided

Mifune-machi

Jewel bug temporary construction housing complex (16)

Design completion

May 29

August 18

 

Amagi temporary construction housing complex (eight)

Design completion

May 29

August 18

 

 

  • Even Kumamoto art police Facebook sends information about "house of all".

 

 

 

  • We maintain "house of all" in small temporary housing less than 20! (at January 27, 2017)


We maintain "house of all" in small temporary housing less than 20!

  •  About small temporary housing less than meeting facility maintenance standard by the Disaster Relief Act, it is Japanese foundation our town foundation ※Utilize 1; and the following housing complexes ※It was decided to maintain nine "houses of all" to 2 sequentially from the end of this month.
  •  The following designers recommended as "Kumamoto art police business" by one of Commissioner Toyoo Ito art police perform discussion meetings with resident, and this "house of all" reflects opinion for design.
  •  
  • ※The prefecture and Japanese foundation utilize our town foundation of the foundation in 1 last August, and and "maintenance of thes of all the Japanese foundations" announces conduct of "living environment maintenance of temporary housing" (about 50 million yen) (about 250 million yen).
  • ※About maintenance of "house of all" of housing complex of 2, etc., we carry out the municipalities concerned and discussion in Japan with foundation.

 

 

 Small scale temporary housing (11 housing complexes in total) maintaining "house of all" and designer

The municipalities name of a village

Housing complex name

Designer

Kumamoto-shi

sansan 2 chome temporary construction housing complex (16)

Masaki Yahagi (Kyushu Sangyo Univ.) + Kenichiro Ide

Aso-shi

Uchinomaki housing complex (19)

Uto-shi

Border second temporary housing complex (14)

Fumio Uchida + Hideo Nishiyama

 

Border third temporary housing complex (12)

Uki-shi

Territory temporary construction housing complex (ten)

Atsushi Takano (Kagoshima Univ.) + Shuhei Nemoto (Daiichi Inst. of Technology) +KASEI Kagoshima team

 

Magano Hasegawa temporary construction housing complex (13)

Misato-machi

kusunoki flat temporary construction housing complex (15)

Shunsuke Yokoyama (Osaka City Univ.) + Katsuhiro Miyamoto (the university) + Shigeki Maeda (Osaka Inst. of Technology)

Mifune-machi

Jewel bug temporary construction housing complex (16)

 

Amagi temporary construction housing complex (eight)

Uto-shi

New Matsubara temporary construction housing complex (18)

Four Takashi + Kenichi Tagami + Mitsuhiro Tokuda

Minamiaso-mura

Room second temporary housing complex (13)

 

 

<about "house of all" to maintain this time>

1 structure, scale        : Wooden/one-story house/around 30 square meters

The 2 business main constituent         : Kumamoto building house center

3 partners, fund furtherance   : Japan foundation

4 management        : The municipalities (we assign from building house center)

5 construction start of construction (plan)    : The early March and late April

6 completion (plan)   :End of March ...

     

We relate to this page
Inquiry

Department of Civil Engineering Architecture Division art police, UD group
Telephone: 096-333-2537
(ID: 18395)
※When PDF file is attached as materials, Adobe Acrobat(R) is necessary.
When you look at PDF documents, Adobe Reader is necessary. When you are not displayed definitely, please use the latest version.
Kumamoto prefectural government office   〒 862-8570  6-18-1, Suizenji, Chuo-ku, Kumamoto-shi, Kumamoto Tel: 096-383-1111 (main)
Copyright(C) 2015 Kumamoto Prefectural Government. All rights reserved.